Blog

Major infrastructure upgrades coming to Waldo

Over the next few years, the City of Kansas City, Missouri, will invest more than $45 million to upgrade basic infrastructure in the Waldo neighborhood. This includes a total reconstruction of Wornall Road from 74th to 79th Streets. Expect a major reconfiguration at the intersection of 75th Street and Wornall Road to improve traffic flow, as well as safety and accessibility for pedestrians and bicyclists.

Spire Energy is currently installing a new gas line along Wornall Road. The city will also do water main replacement and sewer separation work. Construction of the roadway improvements is anticipated to start in early 2019 and finish in the fall of 2020.

Learn more about the plans and construction timeline:

Wornall Road Improvements

75th Street and Wornall Road Improvements

Comments